1 strop new or renovated after the completion of the construction unit should be carried out various tests and self-test, and should fill out the self-test report.
2 Test requirements:
2.1 test speed shall not exceed 8m / s (4 levels);
2.2 Test load of rated load and overload (overload 25%) test;
2.3 manned test, you must use the analog load;
2.4 In doing simulated load test, should be the same as normal when the load's center of gravity;
2.5 various tests, the test should be a permanent deformation of the parts and damage;
2.6 tests do test record, and archived.
3 amusement parks equipment NDT:
3.1 NDT testing using 20 percent sampling;
3.2 using magnetic particle or penetrant inspection methods and quality assessment should be in accordance with JB4730-1994 "Pressure Vessel NDT" in the relevant provisions, inspection and quality rating of not less than grade Ⅲ;
3.3 using ultrasonic testing methods and quality assessment should follow GB/T4162-1991 "Forged steel bars ultrasonic inspection methods" the relevant provisions, inspection and quality rating of not less than A-level.
4 appear serious deficiencies listed, it must be put into use only after completion of the rectification.